West Lorne Ontario Plant Updates

Update: 3rd March, 2008

BioOil Production Re-Starts at West Lorne Facility; Upgrade of Plant Completed

Pictures of BioOil production run, February 29, 2008

Update: 21st January, 2008

Commissioning has started at West Lorne with piping work and electrical work completed and instrumentation being installed and tested. Subject to plant inspections by related authorities, hot commissioning is expected to commence in early February with production to follow soon thereafter.

In preparation for start up, the 2.5 mwe cogeneration package will be inspected by Magellan Aerospace technical staff.

Dynamotive has contracts that cover the total output of the West Lorne plant and given the revenue potential this plant carries, great attention to detail is being provided to the process of completion and start-up.

Once in operation, Dynamotive will be the only company to have two commercial plants in operation producing liquid biofuels from cellulosic residues. Further, this milestone will mark the completion of capital expenditure in Guelph and West Lorne.

Update: 6th November, 2007

Guelph and West Lorne operations continue to progress as planned. Guelph operational teams are on site in preparation for training and handover of plant to Evolution Biofuels which owns and operates the plant under commercial arrangments with Dynamotive. As the Guelph plant commissioning nears completion, negotiations for the sale and supply of biofuels from Guelph and West Lorne are taking place. As well there is continued development work in connection with new potential products from our biofuels.

Dynamotive continues to make substantial progress in implementing its business plan, and is actively moving a large number of business development opportunities forward in Latin America, Canada, Europe, Australia and the U.S.

The Company will provide an update on its Guelph and West Lorne activities, including plant commissioning, biofuels marketing, and product development, when the Q3 results are filed on or before November 29th. Material facts will continue to be disclosed as they occur. All updates are subject to forward looking information disclaimers included on all Company news releases.

Update: 20th September, 2007

West Lorne progresses toward commissioning:

The biofuel plant is advancing toward mechanical completion of the 130 tonnes per day upgrade.

Mechanical erection 97% progress achieved: Work on the quench-column and char-screw advances

Electrical and Instrumentation: Control room electrical installation continues

Insulation: Insulation for reactor’s associated equipment continues - waiting for completion of cyclones and quench column area to begin insulation activities

Piping: Installation progresses at site, work focuses on the cooling-system, air and vent lines

Material changes will be made public as they occur.

Update: 22nd August, 2007

Plant upgrade continues to progress at the West Lorne site.

Mechanical:
Final alignment and leveling of mechanical equipment readying for integration and connection to existing equipment.
Installation of the primary and secondary char separation cyclones is complete.

Electrical:
Wiring for the control room electrical panel and installation of cables into the installed cable trays in progress.

Control System Programming and Upgrade:
Factory Acceptance Test (FAT) passed . Control system program ready for implementation on site.

Insulation:
Contractor on site and the insulation work on the reactor and duct has begun.

Piping:
Piping installation and fabrication in progress .

Next update: Thursday 20th September PM, PST.  West Lorne updates will be provided monthly – material changes will be made public as they occur.

Update: 27th July, 2007

All foundation work on pyrolysis plant upgrade completed

Mechanical installation on pyrolysis plant upgrade continues to progress:

  • Mechanical Installation of lock-bins, char tubular conveyor, and air and nitrogen equipment completed
  • Mechanical installation of piping and platforms in progress
  • Ducting from heating system to stack, sawdust tubular conveyor, air tank, and transition pieces in progress
First and second shipments of steam generation unit received

Electrical and Instrumentation work continues

Civil detail design and permitting for steam generation in progress

Next Update: Wednesday 22nd August PM PST

Update: 29th June, 2007

Foundation for reactor, heating system, nitrogen plant, char transfer unit, pneumatic feed system and char lock bins completed

Mechanical erection near completion:

  • Installation and assembly of the reactor heating system and duct connection with reactor completed
  • Duct modifications and adjustments completed
  • Installation of piping, platforms, lock-bins, tubular conveyor, and air and nitrogen equipment is in progress

Piping fabrication is in progress
Steam generation unit fabrication is in progress

Electrical and instrumentation work continues as planned

Next Update: Friday 27th July PM PST

Update: 8th June, 2007

Work continued at site in accordance to plan; with work concentrating on foundations for installation of nitrogen and other support systems

Mechanical work is progressing with duct work for reactor and burner system completed

Piping work and electrical contractors have commenced their operations at site

Generation System: Maintenance carried out – evaluation for potential capacity increase launched

The next three weeks will see completion of foundation work on pyrolysis system and installation of subsystems on site

Photographic updates will continue regularly

Next Update: Friday 29th June PM PST

Update: 1 June, 2007

Reactor and burner system: Duct work installation verified to fit. Ducts shipped to supplier for refractory insulation work to be completed

Structural work progressing with the second level structure ready to receive equipment

Nitrogen system: Nitrogen tank received and foundations laid in preparation for its installation

Char handling: Equipment received and foundations laid

Mechanical installation continues as planned

Piping contract completed

Electrical contract completed

Click Here for Photographs

Next Update: Friday 8th June PM PST

Update: 25 May, 2007

Work continues steadily on integration of burner and reactor system, duct work integrating burner and combustion chamber received and being installed. Civil works and laying of foundations for new equipment progressing as scheduled. Photographic updates will continue regularly

Next update: Friday 1 June PM PST

Update: 21 May, 2007

Reactor and Burner Installation completed Sunday; Photos available in Album

Next update: Friday 25 May PM PST

Update: 18 May, 2007

Upgraded Reactor arrives on site

Next Update: Monday 21 May, 2007 PM PST